Massachusetts Institute of Technology

Back to Projects: GalleryMapList

Jump to: Select a project

Complete

Central Utilities Plant upgrade, Building 42C

The upgraded Central Utilities Plant (CUP) helps MIT lower emissions, improve campus resiliency and sustainability, and maintain a more flexible power system for incorporating future innovations.

-71.0936000000 42.3616000000
CUP viewed from Albany St (Courtesy Ellenzweig)

Central Utilities Plant upgrade, Building 42C

59 Vassar Street, Cambridge, MA

Status: Complete

Themes: Renovation and renewal
Sustainability

Completion: 2021

The upgraded Central Utilities Plant (CUP) helps MIT lower emissions, improve campus resiliency and sustainability, and maintain a more flexible power system for incorporating future innovations.

Overview

CUP viewed from Albany St (Courtesy Ellenzweig)
CUP viewed from Albany St (Courtesy Ellenzweig)
CUP Lobby (Courtesy Ellenzweig)
CUP Presentation Space (Courtesy Ellenzweig)
CUP Stairwell (Courtesy Ellenzweig)
Interior view of control room (Illustration courtesy of Ellenzweig)

Status

Complete

Completion Date

2021

Themes and priorities

Renovation and renewal
Sustainability

Since 1995, MIT has produced a portion of its own power on campus through a highly efficient combined heat and power (CHP) process, also known as cogeneration. Cogeneration uses one fuel to generate two types of energy: electrical and thermal. By capturing and using heat that would otherwise go to waste, cogeneration reduces the overall fuel consumed, increasing the efficiency of the process and making it one of the cleaner and most cost-effective energy production options available.

When the natural gas turbine in the Central Utilities Plant (CUP) reached the end of its useful life, MIT upgraded the facility, replacing the original turbine with two 22-megawatt turbines, each coupled to a heat recovery steam generator. Two new steam-driven chillers to create cooled air were also installed, along with a 2-megawatt emergency engine, new cooling towers, and state-of-the-art controls to reduce pollutants.

The upgraded CUP now runs entirely on natural gas, eliminating the use of fuel oil on campus except for emergencies and testing. Energy efficiency has increased due to new equipment and controls as well as the system's ability to combine loads for multiple buildings, creating economies of scale. Regulated pollutant emissions (including nitrogen oxides) and greenhouse gas (GHG) emissions have been reduced, and the plant's Increased capacity and reliability serve to boost campus resiliency. In most situations when outside power is lost, the new turbines are designed to start up in the absence of external power and maintain or restore heat and electricity for the majority of campus, safeguarding residences and protecting vital research.

By upgrading its cogeneration energy resource, MIT created a flexible power system that positions the Institute to explore emerging sustainability and efficiency measures. Able to adapt and evolve in response to advances in the energy field, the expanded plant is central to MIT’s commitment to reduce greenhouse gas emissions at least 32% by 2030.

Image credits

Courtesy Ellenzweig

Details

Address

59 Vassar Street, Cambridge, MA

Use

Administrative

Project Team

Engineering: Vanderweil Engineers’ Power Group, Boston, MA,
Architect:
Ellenzweig, Cambridge, MA (original architect of plant building: William Welles Bosworth)
Construction manager:
Bond Brothers, Everett, MA
MIT Team:
Frances Boyle, David Brown, Ken Packard

Scope

89,160 gsf

Design Features

  • Two new 22-megawatt natural gas turbines and heat recovery steam generators provide electricity, steam, and chilled water to campus
  • New turbines can be started even in the absence of external power
  • Plant equipment is designed and sited to keep key components above the anticipated 500-year flood level
  • For campus buildings connected to the CUP, the upgraded plant can meet 100% of electrical needs (up from 60%) during most operating and weather conditions
  • Location inside the plant for new Eversource regulator station (supported by MIT's dedicated transmission gas line) gives MIT access to high-pressure gas and increases Eversource's capacity and ability to provide reliable gas service

Sustainable Design Elements

  • High-efficiency cogeneration process that uses one fuel (natural gas) to produce two types of energy (electric and thermal)
  • Upgraded to run entirely on natural gas except in emergencies and testing situations
  • Best Available Control Technology (BACT) incorporated
  • State-of-the-art emissions controls and equipment incorporated that reduce greenhouse gas emissions by at least 10% from 2014 levels (offsetting an emissions bump in 2020 based on new buildings and program growth) and reduce regulated pollutant emissions more than 25% from 2014 levels; selective catalytic reduction reduces NOx (nitrogen oxides) emissions by 90%
  • Dedicated continuous emissions monitoring system (CEMS) is employed 
  • Backup boilers now burn either natural gas or #2 fuel oil (converted to entirely eliminate the use of #6 oil on campus)
  • Rooftop system captures rainwater for use in the facility’s cooling towers, easing the burden on the city storm water system; storm water on the perimeter site area is captured by rain gardens and through groundwater recharge
  • New cooling towers with high-efficiency drift eliminators reduce particulate emissions and conserve water
  • Lower demand for energy from outside sources, increasing the ability of local utilities to distribute resources as needed
  • Ability to export power to the New England grid if needed when the grid is stressed, reducing the regional burden during an area power-loss situation
  • Ability to import any amount of electricity from the grid, up to 100% of campus needs, if and when the grid becomes a cleaner option than on-campus power generation

Map

42.3616000000
-71.0936000000
15